Skagit River bridge on I-5 to reopen Wednesday

MOUNT VERNON — The Skagit River bridge on I-5 is slated to reopen Wednesday with slower speeds for vehicles and a ban on trucks hauling excessively large cargo like the one which caused it to crumble into the water.

A temporary four-lane span will open without fanfare just shy of a month after a semi-truck carrying an oversized load struck several of the bridge’s overhead trusses, causing a 160-foot section to fall into the river.

Two vehicles went into the water but the three people traveling in them survived the harrowing May 23 incident.

Gov. Jay Inslee visited the site Tuesday as workers paved and prepared to stripe the roadway, a major artery for commuters and commerce that carries an average of 71,000 vehicles a day.

There will be some new rules when the bridge reopens.

The maximum speed will be 40 miles per hour, down from the 60 mph limit in effect before the collapse. That’s because each of the four temporary lanes will be 11 feet wide, which is about a foot narrower than those on the section that fell into the water.

Nearly all cars, commercial vehicles and big rigs carrying legal loads allowed on the bridge before will be able to use it again, transportation officials said.

There will be a barrier between north and south traffic, but it will be made of steel trusses instead of the concrete that separates traffic on the rest of the bridge.

What won’t be allowed are trucks that require a special permit to travel on state highways because they exceed legal rules for height, width, weight or length, said Travis Phelps, a Washington Department of Transportation spokesman.

“If you’re getting a permit to drive on the highway, you won’t be going over this bridge. You’ll be using the detour routes,” he said.

Time-lapse video by WSDOT.

All traffic has been detoured since May 23 when the truck struck the 58-year-old span.

The Washington State Patrol and National Transportation Safety Board are conducting investigations in the cause of the collapse.

Atkinson Construction of Renton received a $10 million contract to demolish the damaged portion, remove debris from the water and put in the temporary four-lane segment that Acrow Bridge of New Jersey built.

On Tuesday, the state awarded a $6.9 million contract to Max J. Kuney Co. of Spokane to construct the permanent replacement span.

Under the contract, work must be done by Oct. 1. It will require closing the bridge for up to two weeks in September to put the span in place, but the closure cannot occur until after Labor Day, according to contract documents.

When the bridge is restored to its pre-collapse capacity this fall, it will still be rated as “functionally obsolete” because it was not designed to handle today’s traffic volume and big trucks. It’s also considered “fracture critical,” meaning that if a single, vital component is compromised, the bridge can crumple again.

Federal funds will cover 100 percent of the costs of the temporary fix and 90 percent of the permanent replacement.

Thus far the federal Department of Transportation has committed $16.6 million for the two projects from its Emergency Relief Fund. The federal agency provided $1 million in the days following the collapse and then last week pledged another $15.6 million.

With the announcement of the scheduled bridge reopening, Amtrak plans to cancel the extra round-trip train it added between Seattle and Bellingham following the span’s May 23 collapse.

Two round-trip Amtrak Cascades trains per day still run between Seattle and Vancouver, B.C. Amtrak also operates five round-trip Thruway Motorcoach buses between the two destinations.

Reporter Bill Sheets contributed to this story.

Jerry Cornfield: 360-352-8623; jcornfield@heraldnet.com

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

A firefighter stands in silence before a panel bearing the names of L. John Regelbrugge and Kris Regelbrugge during the ten-year remembrance of the Oso landslide on Friday, March 22, 2024, at the Oso Landslide Memorial in Oso, Washington. (Ryan Berry / The Herald)
‘Flood of emotions’ as Oso Landslide Memorial opens on 10th anniversary

Friends, family and first responders held a moment of silence at 10:37 a.m. at the new 2-acre memorial off Highway 530.

Julie Petersen poses for a photo with images of her sister Christina Jefferds and Jefferds’ grand daughter Sanoah Violet Huestis next to a memorial for Sanoah at her home on March 20, 2024 in Arlington, Washington. Peterson wears her sister’s favorite color and one of her bangles. (Annie Barker / The Herald)
‘It just all came down’: An oral history of the Oso mudslide

Ten years later, The Daily Herald spoke with dozens of people — first responders, family, survivors — touched by the deadliest slide in U.S. history.

Victims of the Oso mudslide on March 22, 2014. (Courtesy photos)
Remembering the 43 lives lost in the Oso mudslide

The slide wiped out a neighborhood along Highway 530 in 2014. “Even though you feel like you’re alone in your grief, you’re really not.”

Director Lucia Schmit, right, and Deputy Director Dara Salmon inside the Snohomish County Department of Emergency Management on Friday, March 8, 2024, in Everett, Washington. (Ryan Berry / The Herald)
How Oso slide changed local emergency response ‘on virtually every level’

“In a decade, we have just really, really advanced,” through hard-earned lessons applied to the pandemic, floods and opioids.

Ron and Gail Thompson at their home on Monday, March 4, 2024 in Oso, Washington. (Olivia Vanni / The Herald)
In shadow of scarred Oso hillside, mudslide’s wounds still feel fresh

Locals reflected on living with grief and finding meaning in the wake of a catastrophe “nothing like you can ever imagine” in 2014.

Everett mall renderings from Brixton Capital. (Photo provided by the City of Everett)
Topgolf at the Everett Mall? Mayor’s hint still unconfirmed

After Cassie Franklin’s annual address, rumors circled about what “top” entertainment tenant could be landing at Everett Mall.

Everett
Everett man sentenced to 3 years of probation for mutilating animals

In 2022, neighbors reported Blayne Perez, 35, was shooting and torturing wildlife in north Everett.

Dorothy Crossman rides up on her bike to turn in her ballot  on Tuesday, Aug. 1, 2023 in Everett, Washington. (Olivia Vanni / The Herald)
Everett leaders plan to ask voters for property tax increase

City officials will spend weeks hammering out details of a ballot measure, as Everett faces a $12.6 million deficit.

Starbucks employee Zach Gabelein outside of the Mill Creek location where he works on Friday, Feb. 23, 2024 in Mill Creek, Washington. (Olivia Vanni / The Herald)
Mill Creek Starbucks votes 21-1 to form union

“We obviously are kind of on the high of that win,” store bargaining delegate Zach Gabelein said.

Lynnwood police respond to a collision on highway 99 at 176 street SW. (Photo provided by Lynnwood Police)
Police: Teen in stolen car flees cops, causes crash in Lynnwood

The crash blocked traffic for over an hour at 176th Street SW. The boy, 16, was arrested on felony warrants.

The view of Mountain Loop Mine out the window of a second floor classroom at Fairmount Elementary on Wednesday, Jan. 10, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
County: Everett mining yard violated order to halt work next to school

At least 10 reports accused OMA Construction of violating a stop-work order next to Fairmount Elementary. A judge will hear the case.

Imagine Children's Museum's incoming CEO, Elizabeth "Elee" Wood. (Photo provided by Imagine Children's Museum)
Imagine Children’s Museum in Everett to welcome new CEO

Nancy Johnson, who has led Imagine Children’s Museum in Everett for 25 years, will retire in June.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.