Progress slow in Seattle Highway 99 tunnel

SEATTLE — The world’s largest tunneling machine has only drilled 24 feet in a month to create a new route for Highway 99 under downtown Seattle.

The Seattle Times reported a delay on fiberglass strands that became stuck near the cutting face of the drill and a now a labor dispute has disrupted the excavation along Seattle’s waterfront.

Officials say the pace is about two weeks behind what the team expected.

Before drilling began, state officials estimated it would progress at 6 feet per day to start, and eventually accelerate to 35 feet per day in good soil under downtown.

The 1.7-mile dig is supposed to be finished by fall 2014, and the new Highway 99 tunnel to open at the end of 2015.

Officials say they aren’t worried, at this early stage, about missing the schedule.

The project’s 250 workers, at the launch pit in Sodo, are still performing tasks such as putting the arc-shaped tunnel segments into position, and adjusting the drill.

“We’re not laying off, we’ve shortened some shifts and are canceling some others,” said Chris Dixon, project director for the Seattle Tunnel Partners team.

After the July 30 start, bunches of fiberglass strands, 2 feet long and as much as an inch thick, began to clump at the bottom of the machine, just behind the cutting face, Dixon said.

That spot is where the dirt is scooped up by a red screw conveyor that spins within a big tube, nudging the soil toward the rear of the machine — where it’s dropped onto a conveyor belt headed to Terminal 46.

Fiberglass jammed the screw.

Contractors anticipated some difficulty, but the fiberglass caused more trouble than expected. Bertha has bigger openings in the cutter head than most drills, so it didn’t chew the fiberglass into manageable pieces, Dixon said.

Seattle transportation officials expect a slow start, said spokesman Rick Sheridan. The $2 billion tunnel is the most difficult segment of the state’s $3.1 billion replacement for the 1950s Alaskan Way Viaduct, which is at risk of failure in a severe earthquake.

———

Information from: The Seattle Times, http://www.seattletimes.com

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

Girl, 11, missing from Lynnwood

Sha’niece Watson’s family is concerned for her safety, according to the sheriff’s office. She has ties to Whidbey Island.

A cyclist crosses the road near the proposed site of a new park, left, at the intersection of Holly Drive and 100th Street SW on Thursday, May 2, 2024, in Everett, Washington. (Ryan Berry / The Herald)
Everett to use $2.2M for Holly neighborhood’s first park

The new park is set to double as a stormwater facility at the southeast corner of Holly Drive and 100th Street SW.

The Grand Avenue Park Bridge elevator after someone set off a fire extinguisher in the elevator last week, damaging the cables and brakes. (Photo provided by the City of Everett)
Grand Avenue Park Bridge vandalized, out of service at least a week

Repairs could cost $5,500 after someone set off a fire extinguisher in the elevator on April 27.

Riaz Khan finally won office in 2019 on his fifth try. Now he’s running for state Legislature. (Kevin Clark / The Herald)
Ex-Democrat leader from Mukilteo switches parties to run for state House

Riaz Khan resigned from the 21st Legislative District Democrats and registered to run as a Republican, challenging Rep. Strom Peterson.

Shirley Sutton
Sutton resigns from Lynnwood council, ‘effective immediately’

Part of Sutton’s reason was her “overwhelming desire” to return home to the Yakima Valley.

Michelle Bennett Wednesday afternoon during a meet-and-greet with Edmonds Police Chief finalists at the Edmonds Library on August 4, 2021.  (Kevin Clark / The Herald)
Edmonds police chief accidentally fires gun inside police vehicle

Michelle Bennett was at a city fueling facility when her gun went off. Nobody was injured. Edmonds Mayor Mike Rosen was reviewing the incident.

Logo for news use featuring the municipality of Darrington in Snohomish County, Washington. 220118
Gunshot prompts massive police response near Darrington; ends peacefully

A man wanted for robbery fired a shot when deputies converged. Authorities shut down Highway 530 near Darrington. No deputies were injured.

Everett
Dog rescued, 10 displaced after apartment fire south of Everett

Fire crews rescued a dog from the third floor of an apartment building, where sprinklers confined the fire.

Marysville
Marysville man arrested in alleged murder conspiracy in Anacortes

Jesse Michael Allen, of Marysville, is the fifth suspect police believe participated in an alleged kidnapping in September.

Construction occurs at 16104 Cascadian Way in Bothell, Washington on Tuesday, May 7, 2024. (Annie Barker / The Herald)
What Snohomish County ZIP codes have seen biggest jumps in home value?

Mill Creek, for one. As interest rates remain high and supplies are low, buyers could have trouble in today’s housing market.

Rylee Fink, 3, left, stomps through the sand while other children run through the water during a low tide at Howarth Park on Tuesday, May 7, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Stock up on sunblock: Highs in 80s could be coming to Snohomish County

Everett could hit a high of 79 on Saturday. Farther inland, temperatures could reach as high as 86 this weekend.

Neighbors stand in Lisa Jansson’s yard to get a view of the wall of processed wood remains, or “hog fuel,” building up along the property’s border with DTG on Tuesday, March 5, 2024, in Snohomish, Washington. (Ryan Berry / The Herald)
After complaints, county shuts down DTG’s Maltby recycling facility

For months, neighbors have reported constant noise and pollution at the facility. By July 15, DTG must stop accepting material there.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.