Work on 102-year-old Broadway bridge will be delayed

EVERETT — A hobbled downtown bridge may survive a bit longer into decrepit old age, but its days are still numbered.

Everett city engineers had hoped to begin tearing down the 102-year-old Broadway bridge early this year.

Funding issues knocked that schedule out of whack.

The city now hopes to put the project out to bid by the end of June — about eight months later than anticipated.

“We don’t expect the full closure of the bridge to happen until early 2015, but that will be up to the contractor,” city spokeswoman Meghan Pembroke said. “The closure would have started this spring, so it’s close to a year delay.”

The Broadway bridge span crosses the railroad tracks between Hewitt Avenue and California Street.

Initial preparation could be under way by fall.

A Burlington Northern Santa Fe policy, however, prevents construction work from taking place above the tracks from October through December. The railroad imposes the restriction to keep rail traffic moving during the busy holiday season, BNSF spokesman Gus Melonas said.

The Broadway bridge carries an average of 30,000 cars daily.

The 1912 bridge was last renovated in 1931. At least a half-dozen sister bridges built over the railroad tracks around the same time already have been replaced, Pembroke said.

City inspectors for years have warned that the Broadway span was in need of replacement.

In 2008, engineers placed load restrictions on the bridge. They also placed the shoulders off limits to parking and asked truck drivers to stay in the middle lanes, where the structure is stronger.

Inspectors returned within the past month and declared the structure safe to use for the near future, Pembroke said.

Once under way, construction is expected to last up to a year.

The planned closure would prevent people from driving Broadway between Hewitt Avenue and California Street for up to a year. The city intends to warn drivers well in advance, through signs along I-5 and Highway 529.

The bridge replacement budget is $13.6 million, Pembroke said. That includes design work. Construction itself is estimated to cost up to $9 million.

Funding issues came up last year when a state bridge grant the city had been counting on didn’t come through, she said. Instead, the city plans to cover a $970,000 shortfall with traffic mitigation fees that it has collected from developers.

BNSF is contributing more than $800,000 toward the project.

Much of the remaining funding comes from a federal grant.

The new bridge should look similar to the arched Pacific Avenue bridge near Everett Station.

Noah Haglund: 425-339-3465; nhaglund@heraldnet.com.

Talk to us

> Give us your news tips.

> Send us a letter to the editor.

> More Herald contact information.

More in Local News

People line up to grab food at the Everett Recovery Cafe on Wednesday, Dec. 4, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Coffee, meals and compassion are free at the Everett Recovery Cafe

The free, membership-based day center offers free coffee and meals and more importantly, camaraderie and recovery support.

Washington Gov. Jay Inslee proposed his final state budget on Tuesday. It calls for a new wealth tax, an increase in business taxes, along with some programs and a closure of a women’s prison. The plan will be a starting point for state lawmakers in the 2025 legislative session. (Jerry Cornfield / Washington State Standard)
Inslee proposes taxing the wealthy and businesses to close budget gap

His final spending plan calls for raising about $13 billion over four years from additional taxes. Republicans decry the approach.

Devani Padron, left, Daisy Ramos perform during dance class at Mari's Place Monday afternoon in Everett on July 13, 2016. (Kevin Clark / The Herald)
Mari’s Place helps children build confidence and design a better future

The Everett-based nonprofit offers free and low-cost classes in art, music, theater and dance for children ages 5 to 14.

The Everett Wastewater Treatment Plant along the Snohomish River on Thursday, June 16, 2022 in Everett, Washington. (Olivia Vanni / The Herald)
Everett water, sewer rates could jump 43% by 2028

The rate hikes would pay for improvements to the city’s sewer infrastructure.

Everett
Police believe Ebey Island murder suspect fled to Arizona

In April, prosecutors allege, Lucas Cartwright hit Clayton Perry with his car, killing him on the island near Everett.

The bond funded new track and field at Northshore Middle School on Thursday, Oct. 24, 2024 in Bothell, Washington. (Courtesy of Northshore School District)
Northshore School District bond improvements underway

The $425 million bond is funding new track and field complexes, playgrounds and phase one of two school replacements.

Side Out Pickleball Centers co-owner Frank Espinoza inside the newly opened facility in south Everett on Wednesday, Dec. 18, 2024. (Olivia Vanni / The Herald)
‘Demand is really high’ at new south Everett indoor pickleball courts

The sport, invented on Bainbridge Island, is one of the fastest growing in the country.

Jeffrey Allen Cook is arraigned via video at the Snohomish County Courthouse on Thursday, Oct. 4, 2018 in Everett, Wa. HE was arrested on charges of sexual assault on girls in Edmonds. (Andy Bronson / The Herald)
Man with sex crime history sentenced for indecent exposure in Lynnwood

Jeffrey Cook was on probation when he exposed himself at a local thrift store.

Bothell
Speed limit drops on stretch of Bothell Everett Highway

The Bothell City Council approved the change over the summer. Now it’s in effect.

Amtrak Cascades train 517 to Portland departs from Everett Station on Saturday, Sep. 2, 2023, in Everett, Washington. (Ryan Berry / The Herald)
Federal money moves Pacific Northwest high-speed rail forward

The $50 million will fund route planning, community outreach and more. It could have a stop in Everett.

Cars drive along West Marine View Drive past a derelict barge visible off of the shoreline on Wednesday, Dec. 18, 2024 in Everett, Washington. (Olivia Vanni / The Herald)
Port of Everett to remove derelict barge early next year

State funding will support the port’s progress on environmental restoration at Bay Wood.

Students run past older portable classrooms at Glenwood Elementary on Monday, Sept. 9, 2024 in Lake Stevens, Washington. (Olivia Vanni / The Herald)
‘We need more buildings’: Lake Stevens to try same $314M school bond

The bond would build new schools and update others. An attempt in November narrowly failed.

Support local journalism

If you value local news, make a gift now to support the trusted journalism you get in The Daily Herald. Donations processed in this system are not tax deductible.